Title: Explanation of the Supreme People’s Court on the Problem of Application of Laws concerning Disputing Cases of Engineering Construction Contracts Promulgating Organ: The Supreme People’s Court Date of Promulgation: October 25, 2004 Date of Implementation: January 1, 2005 Applicable Scope: The Problem of application of laws concerning disputing cases of engineering construction contracts Major Contents: The circumstance concerning engineering construction contracts to be determined for invalidation is prescribed in the Explanation. The circumstance concerning that a contrast-issuing party shall bear liability for wrong is also stipulated in the Explanation. |
|
|||